KBA press arrived at our Castleford site on Monday 3rd August. The installation is going to plan and once it is completed, a period of staff training will commence. The press should be up and running mid September. Below are some photos of the installation.

Picture 1 above is the new water chiller, Picture 2 is the internal piping from the water chiller and Picture 3 is the new flooring. All of these were installed prior to the arrival of the press.

Tight squeeze for the specialised fork lift truck moving the parts into place. First two units are moved into place and the workstation.

Installation going well now into week 3, power testing to be done later in the week ending 21st August. Press minders getting excited to begin their training which will hopefully start week commencing 24th August.
If you would like to find out more then please get in touch at estimating@pts.ink.